Keep the installation drawing number and revision beside the site survey date. Retain the cabinet position labels from the drawing in the survey notes and photographs. For each difference, record the position, both measurement endpoints, and the drawn and measured dimensions. Use the same reference line and fixed height datum for both values. Attach a numbered photograph or sketch showing the endpoints. A note such as "B2 space is smaller" does not tell the installer where the difference is or how large it is.
For example, the drawing shows an opening of 1800 mm from a wall reference to the inside face of an end panel beside B2. The site measurement between those endpoints is 1760 mm. Record measured minus drawn as 1760 - 1800 = -40 mm, or 40 mm narrower. These are illustrative site values. State what each dimension measures, such as an opening width, a panel position, or a cabinet body. The model records list JY-LC-318 at 555 x 550 x 1900 mm, JY-FS-1D at 620 x 600 x 2010 mm and JY-FS-2D at 1100 x 600 x 2010 mm, in width x depth x height order. Keep these body dimensions in the equipment schedule, separate from the opening measurements.
For a vertical difference, compare readings against the same fixed height datum. Suppose the drawn sign underside is +2200 mm and the measured underside is +2190 mm. Record 2190 - 2200 = -10 mm. If B2 is JY-FS-1D with a proposed body-bottom level of +20 mm, its proposed top is 20 + 2010 = 2030 mm. The gap to the sign changes from 2200 - 2030 = 170 mm to 2190 - 2030 = 160 mm. These example gaps combine a proposed cabinet position with the drawn or measured sign position. They do not describe an installed cabinet measurement or a required ventilation space. Keep measured floor readings separate from proposed body-bottom levels.
Mark each difference on the plan or elevation with a reference, such as S1 for the opening or S2 for the sign. Retain the selected front or rear alignment on the plan. If a revised proposal moves a footprint, identify the previous and proposed positions and the floor readings at each. Record the affected ventilation, door movement, connection, or service-access detail by its equipment drawing reference. Send the measurement list, annotated drawing, and photographs through the inquiry, together with the model code and cabinet label. Retain the original observations when a correction is agreed. The linked correction answer explains how to carry them into the revised drawing.
Prepare this information
- Cabinet labels and photographed endpoints identify each drawn and measured value
- Vertical differences use one fixed height datum and distinguish floor readings from proposed levels
- Selected alignment and numbered observations remain traceable in later corrections
Record the agreed correction in a revised layout